Under constructionApartment

Dubai South · Dubai

Calisi

by Zoya Developments

© Zoya Developments
59of 100
Fromper propertyfinder.ae, 1 Oct 2026
AED 685K≈ $187K
Price, payment plan and homes ↓
The full breakdownWhy 59? See all 8 factor scores and the score history. Free.Unlock free →

Price, payment plan and homes

Price per propertyfinder.ae, 1 Oct 2026
Starting price
AED 685K
≈ $187K
Bedrooms
Studio to 2 bed
400 – 1,250 sqft · 68 units
Payment plan
20/28/10 + 42 post-handover
AED 137K to book
Handover
Q2 2028
0% built per the DLD · likely later

Homes and floor plans

68 homes · Freehold

Pick a home: the plan and the forecast follow it.

Payment plan · studio

On AED 685K
  1. 20% at bookingAED 137K
  2. 28% during construction, until handover (Q2 2028)AED 192K
  3. 10% on handover (Q2 2028)AED 68.5K
  4. 42% after handover (Q2 2028)AED 288K

Before the keys: AED 329K, 48% of the price.

Part of the price is paid after the keys. How post-handover payment plans work.

Zoya Developments’ own file on propertyfinder.ae, checked 30 Sep 2026

Open in the map

Location · Dubai South · Dubai

Masterplan around Al Maktoum International Airport and the Expo site.

Forecast

What the studio could be worth

The in-depth review

Why it scores 59

Price per sqft vs registered sales

Dubai Land Department open data

AED 1,688/sqft (est.)

The DLD median for apartments in Dubai South is AED 1,379/sqft (as of 10 Nov 2026). This project's figure is our estimate from the listed prices and unit sizes, so no gap is shown here; the score's price factor reads it at half weight, capped at 70. The gap appears once the register shows ten of this project's own sales or the developer states a price per sqft.

How the 59 was scored

8 of 8 factors · 100% of the weight · 10 Nov 2026
Confidence: low
How each factor was measured

Each factor with what it was measured on. Its score and the reasoning are in the full breakdown.

Price against what buyers actually paid
Our estimate from its typical home, against the median of 548 off-plan sales in Dubai South · DLD
Developer track record
Our rating and who stands behind it
Payment plan
20% down · 28% during construction · 10% on handover · 42% after
Location and infrastructure
Our rating of Dubai South, and 5 kinds of places measured from the pin · OpenStreetMap
How big the resale market is
531 resales of finished apartments in Dubai South this year · DLD
Construction on schedule
0% built on the DLD register, handover Q2 2028
How much is still being built nearby
12,038 homes sold in Dubai South this year, 95% off-plan · DLD
The basics on file
Registration or escrow number on file · DLD

Confidence low: the price figure is our estimate from the price and size of the typical home, not a registered or stated price.

55 → 59 4 Oct 2026; resale now measuredScored since 24 Sep 2026 · 6 score changes

The formula is public: how the Rendr Score works. Our opinion, not investment advice. A figure you believe is wrong: alexk.dxb02@gmail.com.

Share this score
Show this score on your site

Paste this where the badge should appear. It links back here and updates when the Rendr Score does.

Score card · Change card (1080 × 1350, for posting).

Free · 90 days · the whole site

The full breakdown behind the 59

Free for 90 days. One sign-up opens everything on the site: the breakdown behind all 1,673 scored projects, the figures and reasons behind the developers' ranking, and rent, a mortgage and fees in every forecast. Nothing to pay.

  • All 8 factor scores, with the figure and source behind each
  • Score history since 24 Sep 2026 and why each move happened
  • Rent, a mortgage and fees in the forecast, year by year

Everything behind the 59, and behind every other score on the site.

All fields are required.

+971

Read by the person who runs Rendr, who works in real estate and may contact you about property. Never sold.

I am
Projects scored
1,673
projects scored
Factors
8
factors, formula public
Registers
ADREC · DLD
registered sales, not asking prices

Handover date

Q2 2028

Under construction · 0% built, the DLD's project register, 28 Sep 2026

What this means

Listed as Q3 2027 on 24 Sep 2026. The DLD’s register now expects Q2 2028 (28 Sep 2026).

Also due in 2028 in Dubai South: 23 more projects we list

Zoya Developments: nothing delivered in the last ten years, none cancelled.

Calisi is due to hand over in Q2 2028. Construction is 0% complete according to the DLD's project register (28 Sep 2026). At that progress it cannot hand over by Q2 2028 at any usual building pace. Handover dates are the developer's own estimate and off-plan schedules move, so confirm the current date in writing before paying anything.

DLD registration status

Verified 1 Oct 2026
  • Project registration4512
  • Escrow accountNot published yet
  • Developer licenceNot published yet
Where the figures come from

Check it on dubailand.gov.ae. How to read the DLD register.

Figures from propertyfinder.ae, read 1 Oct 2026, last verified 1 Oct 2026. Construction figure from the DLD's project register, 28 Sep 2026. Launch date from the DLD's project register.

Before you pay: four things to check

  1. 1The escrow accountWe hold no escrow account number. Ask the developer for it, and check it on dubailand.gov.ae before paying.
  2. 2The handover dateThe listed date is Q2 2028. The DLD shows 0% built on 28 Sep 2026, a pace that points to later. Ask for the date in the sales agreement.
  3. 3Today's price listAED 685,000 is a starting price from propertyfinder.ae, 1 Oct 2026. Ask for the unit's own price.
  4. 4The instalment dates20% at booking, 28% during construction, 10% at handover, 42% after handover. Ask for each payment's date and amount.

About

Calisi is Zoya's apartment tower in Dubai South, Dubai, with studios and two-bedroom apartments from about 400 to 1,250 sq ft.

Developer
Zoya Developments
Area
Dubai South
Status
Under construction
Sales launch
31 Aug 2026
Total units
68
Storeys
5
Ownership
Freehold

Amenities

  • CCTV Security
  • Indoor Swimming Pool
  • Landscaped Gardens
  • Restaurants
  • High Speed Elevators
  • Garage
  • Children's Play Area

What’s nearby

straight-line distance
  • Supermarket or mall230 m
  • Hospital or clinic4.0 km
  • School5.4 km
  • Metro or tram stop7.3 km
  • Beach16 km

The nearest of each on OpenStreetMap, Sep 2026.

Rental yield nearby

gross, apartments

7.5% in Dubai South. A median rent of AED 81 per sqft a year on 2,107 new tenancy contracts, last 6 months, against AED 1,082 per sqft paid across 282 finished sales, last 6 months.

Before service charges, fees and empty periods; our arithmetic on Dubai Land Department open data figures, Nov 2026. The working

Calisi: questions buyers ask

How much does Calisi cost?

Prices at Calisi start from AED 685,000 (about $187K) for studios and 2-bedroom homes, per propertyfinder.ae on 1 Oct 2026.

What is the price per sqft at Calisi?

The asking price is around AED 1,688 per sqft, our estimate from the listed prices and unit sizes.

When is the Calisi handover date?

Calisi is expected to hand over in Q2 2028. The project is under construction, 0% built according to the DLD's project register.

What is the Calisi payment plan?

Calisi is offered on a 20/28/10 + 42 post-handover plan: 20% on booking, 28% during construction and 10% at handover, with 42% spread after you get the keys.

What is the Rendr Score of Calisi?

Calisi scores 59 of 100 on the Rendr Score, fair, as of 10 Nov 2026; 8 of its 8 factors are assessed, 100% of the weight.

What rental yield do apartments in Dubai South make?

About 7.5% gross for apartments in Dubai South, worked out from DLD's own figures: new tenancy contracts, last 6 months, against finished sales, last 6 months, before service charges and fees.

Who is the developer of Calisi?

Calisi is being developed by Zoya Developments. It sits in Dubai South, Dubai.

Is Calisi registered with DLD?

Calisi is registered with the Dubai Land Department (DLD) under number 4512. Check it at dubailand.gov.ae before you pay.

Changes

Listed 24 Sep 2026 · 3 changes since, last 28 Sep 2026
  1. Handover moved from Q3 2027 to Q2 2028

    Source: the DLD's project register, 28 Sep 2026

  2. Construction 0% complete

    Source: the DLD's project register, 28 Sep 2026

  3. Sales launch date set to 31 Aug 2026

    Source: the DLD's project register

  4. Listed on the site

    Source: propertyfinder.ae, read 24 Sep 2026