Guide · the Dubai Land Department (DLD)

DLD project status: how to check a Dubai off-plan project

Every off-plan project in Dubai is registered with the Dubai Land Department (DLD), and the register is public. It says who registered the project, how far construction has got and, for the escrow account, where your money is meant to go. This page explains what the register shows and how to read it, then lists the 69 Dubai projects on this site by status: 15 with a project number on file, 15 with an escrow account number and 15 with a construction figure. It is a selection, not the whole register.

Open the register at dubailand.gov.ae

What the register shows for a project

Project number
The DLD's own number for the project. Every registered off-plan project has one; a brochure or sales agreement should quote it, and it is the key to everything else on the register.
Escrow account number
The account the project's buyer payments go into. It is held at a bank under the DLD's supervision and the developer draws on it as construction progresses rather than freely. Pay into this account and no other.
Percent completed
The construction progress the DLD records for the project, as a percentage. It is the register's figure, not the developer's brochure; the DLD's open data shows it for projects registered in the current year.
Start and expected completion dates
When the project was registered as starting, and when it is expected to complete on the register. The expected date is the registered one and is not the same thing as the handover date in a sales brochure.
Unit counts
How many units the project is registered with. The register counts what it counts, which can include parking, retail or commercial units alongside homes.

How to check a project on dubailand.gov.ae

  1. 1

    Ask the developer or the sales agent for the DLD project number and the escrow account number. Both should be in the sales agreement.

  2. 2

    Open dubailand.gov.ae and use the project status lookup to find the project by number. The register shows the developer of record, the percent completed and the escrow account.

  3. 3

    Check that the developer, the escrow account and the completion figure match what you were told. A mismatch is a question for the developer before it is a problem for you.

  4. 4

    Pay into the escrow account shown on the register and no other account, personal or brokerage.

The Dubai projects we list, by status

Each with its DLD number and escrow account where we hold them, and the construction figure where the register or the developer has supplied one. Check every number on dubailand.gov.ae yourself before paying; a selection, not the whole register.

Launched 20

ProjectDLD numberEscrow accountBuilt
BAYZ 101 by DanubeDanube Properties · Business Baynot on filenot on file
Binghatti SkybladeBinghatti Developers · Downtown Dubainot on filenot on file
Bugatti ResidencesBinghatti Developers · Business Baynot on filenot on file
Canal Crown at Business BayDamac Properties · Business Baynot on filenot on file
Como Residences at Palm JumeirahNakheel · Palm Jumeirahnot on filenot on file
Damac Canal Heights 2Damac Properties · Business Baynot on filenot on file
Damac Chic TowerDamac Properties · Business Baynot on filenot on file
DG1 Living TowerDar Al Arkan · Business Baynot on filenot on file
Eden House The ParkH&H Development · Dubai Water Canalnot on filenot on file
Ellington One River PointEllington Properties · Business Baynot on filenot on file
Emaar Bayview by Address ResortsEmaar Properties · Emaar Beachfrontnot on filenot on file
Enara by OmniyatOmniyat · Business Baynot on filenot on file
Jumeirah Living Business BaySelect Group · Business Baynot on filenot on file
Omniyat Vela VientoOmniyat · Business Baynot on filenot on file
Palm Central Private ResidencesNakheel · Palm Jebel Ali415640312269812890020.02%
Raw District 2 by ImtiazImtiaz Developments · Jebel Ali45260016402555688010%
Samana South HavenSamana Developers · Dubai South44720111962470140%
Serro at The HeightsEmaar Properties · The Heights Country Club4237106534418300050.5%
Skyvue Spectra at Sobha Hartland 2Sobha Group · Sobha Hartland IInot on filenot on file
Vela by OmniyatOmniyat · Business Baynot on filenot on file

Under construction 7

ProjectDLD numberEscrow accountBuilt
Binghatti Mercedes Benz PlacesBinghatti Developers · Downtown Dubai2545001137062109665.25%
Burj BinghattiBinghatti Developers · Business Bay2480001137062105652.05%
Damac Canal HeightsDamac Properties · Business Bay2602020583743010236.3%
Palm Beach TowersNakheel · Palm Jumeirah240601900007140282.83%
The CrestmarkEllington Properties · Business Baynot on filenot on file
The QuaysideEllington Properties · Business Bay28151271619692000354.57%
West Bay TowerOrion Real Estate Development · Business Baynot on filenot on file

Ready 42

ProjectDLD numberEscrow accountBuilt
Address Hillcrest VillasEmaar Properties · Dubai Hills Estate24230204806436119100%
AG TowerArabian Gulf Properties · Business Baynot on filenot on file
Ahad ResidencesAhad Group · Business Baynot on filenot on file
Avanti ApartmentsDamac Properties · Business Baynot on filenot on file
Bays EdgeDamac Properties · Business Baynot on filenot on file
Bayz ApartmentsDanube Properties · Business Baynot on filenot on file
Binghatti CanalBinghatti Developers · Business Baynot on filenot on file
Business TowerDamac Properties · Business Baynot on filenot on file
Clayton ResidencyDeyaar · Business Baynot on filenot on file
Creek PalaceEmaar Properties · Dubai Creek Harbour21910205269605309100%
Damac PriveDamac Properties · Business Baynot on filenot on file
Damac The ResidencesDamac Properties · Business Baynot on filenot on file
DAMAC Towers by ParamountDamac Properties · Business Baynot on filenot on file
Dolphin TowerThe First Group · Business Baynot on filenot on file
Edge Business BaySelect Group · Business Bay26110204977502022100%
Elite Business BayTriplanet Range Group · Business Baynot on filenot on file
Executive BayDamac Properties · Business Baynot on filenot on file
J One TowerRKM Durar Group · Business Baynot on filenot on file
MajestineDamac Properties · Business Baynot on filenot on file
Merano TowerDamac Properties · Business Baynot on filenot on file
Millennium Binghatti ResidencesBinghatti Developers · Business Baynot on filenot on file
Nobles TowerTiger Group · Business Baynot on filenot on file
Park CentralDamac Properties · Business Baynot on filenot on file
Peninsula FiveSelect Group · Business Baynot on filenot on file
Peninsula FourSelect Group · Business Bay24610204977502020100%
Peninsula OneSelect Group · Business Baynot on filenot on file
Peninsula TwoSelect Group · Business Bay23180204977502014100%
Regalia TowerDeyaar · Business Bay2270454761830001100%
Reva ResidencesDamac Properties · Business Baynot on filenot on file
Sky Bay HotelThe First Group · Business Baynot on filenot on file
Sol BaySol Properties · Business Baynot on filenot on file
The Atria Business bayDeyaar · Business Baynot on filenot on file
The Court TowerTanmiyat Group · Business Baynot on filenot on file
The OpusOmniyat · Business Baynot on filenot on file
Trillionaire ResidencesBinghatti Developers · Business Baynot on filenot on file
Upper CrestDamac Properties · Business Baynot on filenot on file
Upside Business BaySRG Holding · Business Baynot on filenot on file
Urban OasisDar Al Arkan · Business Baynot on filenot on file
VERA ResidencesDamac Properties · Business Baynot on filenot on file
VolanteXtreme Vision · Business Baynot on filenot on file
XL TowerDamac Properties · Business Baynot on filenot on file
Zada TowerDamac Properties · Business Baynot on filenot on file

All projects in DubaiPrices vs registered salesHow the register feeds the score

Questions about the DLD register

How do I check a DLD project status?
Take the DLD project number from the sales agreement or the developer and look it up on dubailand.gov.ae, run by the Dubai Land Department (DLD). The register shows the developer of record, the percent completed and the escrow account. Every project page here shows the number where we hold it, so it can be checked against the register directly.
What does percent completed mean on the DLD register?
It is the construction progress the register holds for the project, as a percentage, from the register's own inspections and filings rather than the developer's marketing. The DLD's open data publishes it for projects registered in the current year. Where we hold the figure it appears on the project page with the register named as its source.
What is a DLD escrow account number?
The number of the account the project's buyer payments go into, held under the Dubai Land Department (DLD)'s supervision and drawn on by the developer as construction progresses rather than freely. Ask for it, check it on dubailand.gov.ae, and pay into that account only. Our project pages show the escrow account number where we hold it.
Where are DLD transactions published?
the Dubai Land Department (DLD) publishes every registered sale through its open-data portal: the price, the size and the date. We read them each month to compute the median price per sqft buyers paid in each area (sales of homes that were not built yet) and measure every project against it; the emirate page and the monthly price-gap report show the figures.